Most Edinburgh and Lothian terraces date from between about 1850 and 1910, built as long, continuous runs of sandstone rubble masonry on shallow footings. That continuity is the whole problem. A semi or a detached house has space on one or both flanks; a mid-terrace property shares load-bearing walls on both sides and, almost always, a combined drainage run behind it. You are not building on a blank slate — you are adding to a structure that has already settled, shifted and been altered for well over a century.
The constraints that catch people out are rarely glamorous. They are the location of a shared sewer, the depth and condition of a neighbouring foundation, the width of a back green that will never take a concrete wagon. Getting to grips with these early is the difference between a straightforward build and six months of redesign.
It surprises many homeowners that the Party Wall etc. Act 1996 does not apply north of the border. There is no statutory notice procedure in Scotland. Instead you rely on the common law of common interest, the terms of your title deeds, and — where the building is tenemental — the Tenements (Scotland) Act 2004. That does not mean you can do as you please. It means the obligations are less procedural and more case-specific, and good practice matters more, not less.
In practical terms, before any excavation begins:
Victorian terraces in Leith, Marchmont, Bruntsfield or Portobello typically sit on strip footings of rubble or mass concrete, often only 600–900mm below ground level and sometimes less where there is a basement or retaining wall. These footings are wide but weak by modern standards, and they have taken their settlement already.
New extension foundations usually need to be deeper. Where they would undercut the existing wall, the load above has to be spread — traditionally assessed using a line of influence at roughly 45 degrees from the underside of the existing foundation. If your new footing falls inside that zone, expect one of the following:
Ground conditions vary considerably across the region. Boulder clay and glacial till are common, but made ground, old quarries and, in parts of Midlothian and East Lothian, former coal workings all appear. A desk study and, where warranted, a trial pit or borehole will tell you far more than an assumption.
This is the single most common cause of late redesign. Terraces were built with shared combined drains running along the rear, frequently beneath the exact footprint where homeowners want to extend. In Scotland, Scottish Water must be consulted, and a build-over agreement is normally required for any sewer running under a proposed structure. Drains within about three metres of a new foundation may also need protection or diversion.
Commission a CCTV drainage survey before design work starts, not after. It will show the line, depth and condition of every run, and whether a drain is public or private. Diverting a shared sewer is disruptive and needs neighbour cooperation, so the earlier it is identified, the more options you have.
How the extension connects to the existing house is a structural decision, not a detail. A two-storey rear extension has to be tied into the existing wall plate and roof structure adequately for wind loading, while avoiding unnecessary load being shed onto a mutual wall that may be a single leaf of rubble. In older terraces, gable and mutual walls can be thinner and more irregular than they appear from the outside.
If a chimney breast sits within the extension zone, its removal affects the stability of the shared stack above. That needs engineering input, and often a steel frame to carry what the breast was supporting.
In Scotland, structural design is normally certified through the SER scheme, and a Building Warrant is required before work starts — you cannot begin on the basis of a planning approval alone. Terraced properties in conservation areas, and anywhere within the Edinburgh World Heritage Site, also have restricted permitted development rights, so planning permission is usually needed.
The sensible sequence is straightforward: drainage survey, ground investigation, structural engineer, then architect and builder. An engineer who knows Edinburgh's terraces will spot the drainage run, the shallow footing and the thin mutual wall before they become expensive problems. That early hour of advice is almost always the cheapest part of the project.
April 25, 2019 at 10:46 am
Take in the iconic skyline and visit the neighbourhood hangouts that you've only ever seen on TV. Take in the iconic skyline and visit the neighbourhood.
Want to be notified when we launch a new template or an udpate. Just sign up and we'll send you a notification by email.
Soldman Kell
April 25, 2019 at 10:46 am
Take in the iconic skyline and visit the neighbourhood hangouts that you've only ever seen on TV. Take in the iconic skyline and visit the neighbourhood.